Name of the Client:
Kollam Corporation, Asian Development Bank, Govt. of Kerala
Brief description of the Project:
Construction of Electromechanical Compost Plant based upon aerobic composting process, Construction of New Engineering Sanitary Landfill, Rehabilitation & Scientific Closure of Existing MSW dump Site, Construction of Leachate treatment plant based upon activated sludge process & RO system.
Salient Features of the Project:
Capacity of Electromechanical Compost Plant: 100 tpd
Amount of Garbage to be closed under dump Site: 35000 cum
Capacity of Leachate treatment plant : 135 cum/hr
Funding Agency: ADB, Govt. of Kerala
Contract Value: 6.79 (in Rs. Million)
Contract Duration: 18 months
Date of Completion: Feb '09 |